Since Service Pack 1 of Project Server 2007 users have the ability to track progress by “hours per day” as shown below:
To do that you will have to activate the Hours per day setting of the My Tasks web part (edit page (need to be admin) –> Edit –> Modify Shared Web Part –> Project Web Access –> check hours per day) :