Summary
Motley: Estimation is always inaccurate. Individual gut-feel estimation is the only way to go.
Maven: Wideband Delphi is a valuable estimation technique that can immediately improve your accuracy.
______________________________
[Context: Motley is about to estimate the amount of effort to develop a new feature and is reflecting on the difficulty of estimation]
Motley: You know, sometimes I really wonder what the point is of estimation. Developers are never accurate on any project longer than 3 days! The only real way to estimate is to go off gut feel and leverage the PANOOMA technique.
Maven: You're right - estimation is hard. But, fortunately there are some techniques we can leverage to improve the accuracy of our estimates. And by the way, what is the PANOOMA technique of estimation? That's not one I have heard of.
Motley: Pull A Number Out Of My Ass! That's really what ends up happening anyway.
Maven: Ha! Let's just call that "gut feel" estimation from now on, shall we? Anyway, have you tried basing your estimates on past projects?
Motley: Yeah, I try to compare what I am working on now to what I have worked on in the past, but I must admit that I usually miss something and end up blowing the estimate. It's frustrating. My boss doesn't trust me to delivery anything on time these days. I've heard of some more scientific techniques of estimating and some software packages that facilitate a more accurate estimation, but I'm not sold. Many of them also require lots of historical data, which I don't have.
Maven: Have you ever heard of Wideband Delphi estimation? That technique could help you out.
Motley: No, never heard of it. Not sure I want to. It sounds like it's extremely mathematical suited for pocket protector geeks and way overkill for our projects. And NO, I don't want to hear about it.
Maven: That's not the attitude I'm looking for!
Motley: Yeah, well, you're going to tell me anyway, so please just get it over with so I can get back to more meaningful activities, like lunch.
Maven: That's the spirit! I think. Wideband Delphi is a very easy estimation technique to learn. There's really not much to it, and it's not scientific or highly mathematical. Instead, it leverages the wisdom of crowds.
Motley: Hey, I've read that book! It surmises that an uninformed crowd can often make a better prediction than an informed individual. My buddies and I use it all the time when buying our weekly lottery tickets, but it never seems to help.
Maven: You're right on the synopsis, although lottery tickets is not the best application. Wideband Delphi leverages the "wisdom of crowds" concept using the following lightweight process:
Motley: Interesting. You are leveraging the experience of other people to help you with your estimate. I bet once you turn over the estimates in the first round that the numbers are all over the map!
Maven: Almost always! In the first round there are lots of unknowns and everyone has a slightly different take on what it takes to get the job done. When estimating a coding task, Mary may include a code review but Marvin may not. Marty may assume that he is doing the work and has expertise, but Marcus assumes that the new intern is doing the work. The discussion helps focus the team on what is required to get the job done. By learning about everyone's assumptions and making some initial decisions as a team, you inherently lead to more refined and accurate estimates. Plus, you document the team decisions and can back up your numbers to whoever asks, like management.
Motley: But why does everyone have to put their number upside down on a sheet of paper. Why not just tell everyone your estimate?
Maven: Good question! We do this for a couple of reasons. Firstly, you don't want to bias anyone with your number, so you keep it quiet and they are all revealed at once. Additionally, keeping estimates anonymous allows you to go with your gut without being pressured by others in the room. For example, if there is a high ranking architect with lots of experience in the estimation session and everyone hears her number first, they may be inclined to just go with it. However, everyone in the room adds value and should have their assumptions heard. Keeping it anonymous removes a bit of pressure.
Motley: This seems way overkill for a smaller project with fewer unknowns. I'm still back to gut feel estimation and this won't help me much. Unless, genius, you have a solution for that too?
Maven: You know me, Mot. I have a solution for everything! And for that, we need to talk about a related estimation technique called Planning Poker...
Maven's Pointer: The most effective Wideband Delphi sessions involve estimators with different perspectives that also use different estimation techniques to derive their numbers. If one person uses Proxy-based estimation, another uses gut feel, and another uses Function Points, you can be pretty confident that the overall team number is accurate as it was arrived at using various techniques.
Maven's Resources:
PingBack from http://www.artofbam.com/wordpress/?p=2794
If you have Software Project Estimation experience as a IT Project Manager or Business Analyst or IT Architect then you can earn money at our site. We are looking for experienced people in software project estimation techniques who can associate with us online. Check out. We use a technique similar to Delphi.