Adding a red/yellow/green progress indicator

Adding a red/yellow/green progress indicator

  • Comments 10

Hi there! My name is Sonia Atchison, and I write some of the Help content you see over on Office Online. I know this may seem like a silly little blog post to many of you, but I remember when I first started using Project and I figured out how to make a field that showed red/yellow/green graphics to indicate progress, I was pretty happy with myself. So I decided that you know what, I bet there are people out there reading this blog right now that would really appreciate a quick rundown of how to make a visual progress indicator.

Create a custom Progress field

First, you have to create a custom field that will hold your status information. On the Tools menu, point to Customize, and then click Fields. Choose an unused text field, and then click Rename. Type "Progress" and then click OK.

Next, you want to identify the different progress values. Under Custom attributes, click Lookup. Use the table to add three values that correspond to red, yellow, and green. In this example, I'll use "On track," "Issues," and "Blocked." Select the Use a value from the table as the default entry for the field check box, click the value that corresponds with green ("On track"), and then click Set Default. Click Close to return to the Custom Fields dialog box.

Finally, you need to identify which graphics to use for each lookup value. Under Values to display, click Graphical Indicators. Use the table to set each indicator, as I've done here:

clip_image002

Click OK when you have the indicators set, and then click OK again to return to the Gantt Chart view.

Insert the Progress field

Next, add the field as a column in the Gantt Chart view using these instructions. The process is fairly straightforward…just right-click the column header to the right of where you want the new column to appear, click Insert Column, find the Progress column, and then click OK.

Use the Progress field

Once the column is added to the view, you can choose the progress for each task in your project, and the red, yellow, or green indicator will appear in the view. I think this is pretty neat, myself!

clip_image004

Need more info?

A video demo of this process can be viewed here, or a Help topic with similar instructions is available here if you need more information!

  • PingBack from http://www.anith.com/?p=999

  • This is great.  Do the icons work when exporting to an Excel pivot table?  I'm looking for some kind of simple, manual status indicator (like the red, yellow, green) that works in Project and in Pivot Tables.  Thanks!

    Ron

  • Great question, Ron! I wasn't sure of the answer, so I checked with Heather, and she says that when you export to Excel, the indicators aren't transferred. Instead, you get the value behind the indicator. However, you can use conditional formatting in Excel to add the indicators back. For more info on that option, check out these Excel Help topics:

    http://office.microsoft.com/en-us/excel/HP100739391033.aspx

    http://office.microsoft.com/en-us/excel/HA102176291033.aspx

    http://office.microsoft.com/en-us/excel/HA101655491033.aspx

    http://office.microsoft.com/en-us/excel/HA102308411033.aspx

    Hope that helps!

  • This is a well laid out set of instructions which I followed easily with success. Good job.

    I'm a little disappointed that these aren't automatic indicators. On a project with 1,000+ items, it would be a little tedious to set each of these individually...

  • Hi, I have a problem. I am using office 2007, I have SQL Server 2008 and there is Adventureworks cube. I tried to create pivot table in Excel. I connected into cube where there are KPI indicators but In Pivot List I have not seen them? Why?

  • This is a bit lame. As the colours are based on a manual entry for each row, you may as well just go through your plan and manually change the font colour of anything that's ovedue etc.

    An improvement would be to base it on a formula that looks at set criteria & produces a relevant traffic light (e.g. % complete is not set to 100 and the end date is approaching, & make an amber symbol show up)

  • You can create formulas for the custom field that would control the indicator value. To do this, when creating the custom field, in the custom attributes section, define a formula for the field.

  • This is awesome!!!  Thank you!  My first experiences with MS Project was back in the 90s when I played project manager and used Project more as a beautified checklist.  Now that I am an experienced project manager, I use Project to manage my projects and programs.  The stoplight (red/yellow/green) feature is fantastic.  It allows me to show status of tasks to my executives in a user-friendly way.

  • This is a great article,  exactly what I am looking for to create my project report for business.  

    Can you tell me where I can find tool menu in MS project 2010?  

  • Nancy - you can access this through the Custom Fields dialog which is on the Project tab.