Activity: Divide Scenarios into Tasks
Plan an Iteration
Task
Participating Roles
Responsible:
Project Manager
Consult:
Architect
Developer
Tester
A scenario is divided into the development tasks to implement the scenario. Dividing scenarios further provides better cost estimates and divides the work among the developers. Some scenarios might impact multiple subsystems within an application. In this case, separate tasks are created for each affected area. The key to successfully dividing the scenario into tasks is to have developers and testers do the division and encourage them to select their own tasks. All tasks must be selected.
Dependencies:
1
Gather the Team
2
Identify Architecture and Development Tasks
3
Choose Architecture and Development Tasks
4
Reassign Scenario to a Developer
5
Create Test Tasks
6
Choose the Test Tasks
The initial iteration plan contains tasks describing all work necessary to fulfill all the scenarios scheduled for the iteration.
All tasks created during the brief meeting are chosen.