There are some limitations with the task notes field and the PSI which are discussed elsewhere on the blogs with a potential workaround of using VBA to access the RTF information. Another workaround you might consider is to use SharePoint and the Project Read More...
In the dataset for the Project you have read/write access to Task_WBS. Unfortunately this should be read-only and the documentation is being corrected. (See community comment already posted at http://msdn2.microsoft.com/en-us/library/websvcproject.projectdataset.taskrow.task_wbs.aspx#CommunityContent Read More...
The queue is one of the new features that is taking some getting used to by our customers. It is probably time for a fresh "queue problems" posting - that will be my next post, but the following came out of a discussion with Patrick Conlan yesterday. Read More...
I had a recent question concerning an apparent difference between the % complete showing on the Project Center view for a task/project and the % complete showing on My Tasks. If you have more than one assignment and many tasks it can be difficult to reconcile Read More...
If you haven't already seen the announcement on Christophe's blog take a look at the new connector for Visual Studio TFS to Project Server 2007! See http://www.codeplex.com/pstfsconnector/Release/ProjectReleases.aspx?ReleaseId=4887 for further details. Read More...
The session list for the Project 2007 Conference has been posted to the http://www.msprojectconference.com site. Go to http://www.msprojectconference.com/tracks.htm to see the details. Technorati Tags: Microsoft , Project Server , Project Server 2007 Read More...
 